Shire HGT Project Atlas

Work Activity Over the next 4 Weeks Starting October 1, 2009

  • Complete installation of all on site curb;
  • Complete flooring installation in the suites;
  • Elevators 2, 3 and 4, ready for State Inspection;
  • Complete phase # 2 of the landscaping installation;
  • Complete installation of finished site paving;
  • Complete installation of the generator sound wall;
  • Complete all levels of admin punch list and receive client sign off;
  • Substantially complete duct work at Interstitial;
  • Install Fire Alarm devices at process suites and begin pre-testing of area system;