Shire HGT Project Atlas
Work Activity Over the next 4 Weeks Starting October 1, 2009
- Complete installation of all on site curb;
- Complete flooring installation in the suites;
- Elevators 2, 3 and 4, ready for State Inspection;
- Complete phase # 2 of the landscaping installation;
- Complete installation of finished site paving;
- Complete installation of the generator sound wall;
- Complete all levels of admin punch list and receive client sign off;
- Substantially complete duct work at Interstitial;
- Install Fire Alarm devices at process suites and begin pre-testing of area system;
Atlas Construction Progress PDF